Progress: Knatchbull Rd, Electrical

Posted on 26th July 2024

 

Progress: Knatchbull Rd, Electrical

At Under 1 Roof Co. we specialise in transforming homes into comfortable, safe and aesthetically pleasing spaces. We recently embarked on a large project on a six-bedroom house focusing on electrical and plastering work. Here's a detailed look at our process, showing the careful planning and execution that goes into such a project.

Electrical Work: Powering the Heart of the HomeTotal duration: 38 days

Start Date: Wednesday 5th June 2024

End date: Saturday, July 27, 2024

1. Initial Electrical Setup (1st Fix)

Our journey started with the first repair on the 1st and 2nd floor, laying the foundation by installing the necessary wiring and socket boxes. This phase is crucial as it creates the infrastructure for all future electrical installations.

2. Room electrical settings

The next phase involved the utility room where we focused on installing the vital electrical systems that, would power the various utilities and security features in the house.

3. First Floor Electrical Setup (1st Fix)

We then moved downstairs where we did a full kitchen re-wiring, installed a new fuse board, set up TV points and integrated a CAT hub to ensure robust connectivity throughout the house.

4. Final electrical work on the second and first floor (2nd repair)

With the foundations laid, we proceeded to the second repair on the 1st and 2nd floors. This phase included the installation of socket covers, light fixtures and switches to ensure that all installations were functional and aesthetically aligned with the interior design.

5. Final electrical work on the first floor (2nd repair)

We finally completed the second fix downstairs, adding finishing touches to the electrical systems to keep everything running smoothly.

Plastering: Creating the perfect canvas

Start Date: Monday 1 July 2024

End Date: Saturday, July 6, 2024

1. Comprehensive plastering

Once the electrical work was in order, our plastering team moved in to complete the plastering throughout the house, focusing on the studies and the entire first floor. Plastering is a critical step that ensures the walls are smooth and ready for painting, providing the perfect canvas for the final decor.

Importance of detailed planning

Projects this large require careful planning and coordination to ensure everything runs smoothly. Here's why our approach is important:

Efficiency: By sticking to a detailed schedule, we ensure all tasks are completed on time, minimizing disruption to homeowners.

Quality: Each stage is carefully carried out by our experienced professionals, ensuring a high standard of quality construction.

Communication: Regular updates inform and engage our clients, strengthening trust and satisfaction.

Transforming a six-bedroom house requires detailed planning, skilled execution and a commitment to quality. At Under 1 Roof Co. we take pride in our work and ensure that every project is completed to the highest standards. Whether it's laying the foundation with wiring or creating a smooth canvas with plaster, we're committed to making your home a better place to live.

Contact us for a free quote

🔗 www.under1roofco.com
📧 bookings@u1rp.com
📞 0204 532 4279

Back To Blog »

Signup

Subscribe to our newsletter for all the latest news.

Contact Us

Had a recent visit or service?

Leave us feedback to let us know how we did!

Leave Feedback

Have a Query?

Contact Us
© Copyright 2024 Under one RoofWeb Design By Toolkit Websites